Monday 6 September 2010

ADMIRAL Sprint 12 plan

Sprint 12 has been planned to run over the next 3 weeks.

The Sprint 12 planning meeting is reported at:
http://imageweb.zoo.ox.ac.uk/wiki/index.php/ADMIRAL_PlanMeeting_12.

The three main activities scheduled are:

  • Deploy ADMIRAL system for Development group
  • Repository submission testing (mainly coordinating with AR)
  • Implement repository content display

Friday 3 September 2010

ADMIRAL Sprint 11 review

This sprint has been substantially taken up with introducing a new developer to the various ADMIRAL technologies.  Progress (not enough) has been made with improving and debugging the ADMIRAL system generation scripts, but the resulting system is not passing its tests.  Some progress has been made to creating a utility for displaying dataset content in user-friendly fashion.

Review of sprint 11: http://imageweb.zoo.ox.ac.uk/wiki/index.php/ADMIRAL_SprintReview_11